Dear Server Expert,
We have one Physical server running windows server 2008 R2 and inside this Physical Hypervisor there are 3 VMs that running Microsoft Exchange 2010 SP3. Currently, due to the hang to the server, i have to shutted down the server and immediately there are"Merge in Progress" that is running after the server has shutted down. I am not sure why there are this message as i didn't know at all and didn't notice previously that there are Snapshot applied in this server.
Now the issue is, the physical server has lacked of disk space for the merging to finish as i saw that it just left 9 Percent left and it is now only running 28 Percent. The disks are all in dynamics type.
My question is:
1. should i stop the merging? how do i stop the merging? will it stop if i turn on the server again at least to prevent the merging process to start filling the hard disk space?
2. Since they are all dynamic disk, will it work if i plug in one external USB harddisk (1 TB) and convert it to dynamic and then combine the disk space with the server disk space to allow the space for the AVHD to merge?
Please help to advise urgently
Thanks